What happens when
Your bathroom renovation, step by step
What happens at each stage, what you'll need to do, and when you can and can't use the room. On average, a bathroom takes Graham about 10 working days on site.
- Steps 1 to 4: planning, at your pace. The room still works.
- Steps 5 to 10: on site, about 10 working days on average
- Step 11: it's yours again
-
Planning
You get in touch
Call Graham, or send the short form with a few details. If you've used the cost guide, your choices come with it. You'll hear back within 24 hours.
-
Planning
Free advice, on site
Graham comes to you, measures up and talks through your ideas: what's possible, design options, costs and materials. This is where simple tweaks that save thousands come up.
-
Planning
A written quote, no obligation
The quote sets out what's included and your timeline. The person who wrote it is the person who'll build it.
-
Planning
Choices and a start date
Tiles, vanity, tapware and glass are settled, and a start date is booked. Inside Out works on one bathroom at a time, so the date is yours.
-
On site
Strip-out
Tiles, bath, vanity and fittings come out, back to the frame and the slab, and the rubbish goes. In homes built before 1990, old sheeting is checked for asbestos first.
-
On site
Plumbing and electrical
Licensed plumbers and electricians run new pipes, wastes and power in the open walls. Anything moved in the layout is moved now.
-
On site
Walls and floor prepared
Walls are sheeted and the floor is prepared, with the shower floor falling to the drain so water goes where it should.
-
On site
Waterproofing
The floor and wet walls are waterproofed by licensed trades to the Australian Standard, then left to cure before tiling. A quiet day on site is part of doing it properly.
-
On site
Tiling and grout
Floor and wall tiles go on, set out so the cuts land where you won't notice them, then grouted.
-
On site
Fit-off
Vanity, toilet, tapware, shower glass, mirror, lights and accessories go in, and the last bead of silicone is run.
-
Done
Clean, walk-through and handover
The room is cleaned and you walk through it with Graham. Inside Out is a Sunshine Coast business, so if anything needs a look later, Graham is close by.
Questions
Questions about the timeline
How long will I be without a bathroom?
On average, Graham's bathrooms take about 10 working days on site. Your quote gives your own timeline, and if it's your only bathroom a temporary way to shower is planned before work starts.
Do I need to be home while the work is on?
Not all day. Graham will talk through access with you before the start date, and you'll know who's coming and when.
Who will I deal with?
Graham, from the first call to handover. The licensed plumbers, electricians and waterproofers who work alongside are organised for you.
Why is there a day when nothing seems to happen?
Waterproofing has to cure before tiles go on. Rushing it is how leaks start, so a quiet day is part of doing it properly.
Ready for step one?
Call Graham for free advice, or price your bathroom first.