Your bathroom renovation, step by step

What happens at each stage, what you'll need to do, and when you can and can't use the room. On average, a bathroom takes Graham about 10 working days on site.

  • Steps 1 to 4: planning, at your pace. The room still works.
  • Steps 5 to 10: on site, about 10 working days on average
  • Step 11: it's yours again
Is it the only bathroom in the house?
  1. Planning

    You get in touch

    Call Graham, or send the short form with a few details. If you've used the cost guide, your choices come with it. You'll hear back within 24 hours.

    Your partRoughly what you'd like, your suburb, and whether it's your only bathroom.

    Room in use

  2. Planning

    Free advice, on site

    Graham comes to you, measures up and talks through your ideas: what's possible, design options, costs and materials. This is where simple tweaks that save thousands come up.

    Your partShow Graham the room, and any photos of bathrooms you like.

    Room in use

  3. Planning

    A written quote, no obligation

    The quote sets out what's included and your timeline. The person who wrote it is the person who'll build it.

    Your partRead it, ask anything, and take your time.

    Room in use

  4. Planning

    Choices and a start date

    Tiles, vanity, tapware and glass are settled, and a start date is booked. Inside Out works on one bathroom at a time, so the date is yours.

    Your partMake your choices. Clear the bathroom cupboards before day one.

    Room in use

    Showering: this is when your temporary arrangement is planned, so it's ready before the strip-out.

  5. On site

    Strip-out

    Tiles, bath, vanity and fittings come out, back to the frame and the slab, and the rubbish goes. In homes built before 1990, old sheeting is checked for asbestos first.

    Your partExpect noise and dust for the day. Keep pets and little ones clear.

    Room out of action

    Showering: your temporary arrangement starts today.

    Showering: use your other bathroom until handover.

  6. On site

    Plumbing and electrical

    Licensed plumbers and electricians run new pipes, wastes and power in the open walls. Anything moved in the layout is moved now.

    Your partNothing, unless a choice needs a quick decision on the day.

    Room out of action

  7. On site

    Walls and floor prepared

    Walls are sheeted and the floor is prepared, with the shower floor falling to the drain so water goes where it should.

    Your partNothing.

    Room out of action

  8. On site

    Waterproofing

    The floor and wet walls are waterproofed by licensed trades to the Australian Standard, then left to cure before tiling. A quiet day on site is part of doing it properly.

    Your partPatience. Nobody walks on it while it cures.

    Room out of action

  9. On site

    Tiling and grout

    Floor and wall tiles go on, set out so the cuts land where you won't notice them, then grouted.

    Your partA look at the set-out if you'd like one.

    Room out of action

  10. On site

    Fit-off

    Vanity, toilet, tapware, shower glass, mirror, lights and accessories go in, and the last bead of silicone is run.

    Your partNothing yet. Nearly there.

    Room out of action

  11. Done

    Clean, walk-through and handover

    The room is cleaned and you walk through it with Graham. Inside Out is a Sunshine Coast business, so if anything needs a look later, Graham is close by.

    Your partEnjoy the first shower.

    Back in use

Questions

Questions about the timeline

How long will I be without a bathroom?

On average, Graham's bathrooms take about 10 working days on site. Your quote gives your own timeline, and if it's your only bathroom a temporary way to shower is planned before work starts.

Do I need to be home while the work is on?

Not all day. Graham will talk through access with you before the start date, and you'll know who's coming and when.

Who will I deal with?

Graham, from the first call to handover. The licensed plumbers, electricians and waterproofers who work alongside are organised for you.

Why is there a day when nothing seems to happen?

Waterproofing has to cure before tiles go on. Rushing it is how leaks start, so a quiet day is part of doing it properly.